Pierce, WA interconnection queue

1 active project totalling 1 MW in the BPA queue, plus 4 with terminal status (shown greyed).

1active projects
1active MW
5total filed
Queue IDProjectkVMWResourceStatus
G70 Frederickson Power LP n/r 300 Gas WITHDRAWN
G40 250MW Covington-Chehalis,Tacoma-Olympia 230 250 Gas WITHDRAWN
G51 Pierce County Project No 1 230 170 Gas WITHDRAWN
G52 Pierce County Project No 2 230 170 Gas WITHDRAWN
G1090 Not reported n/r 1 Solar STUDY

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.