Substation Scout

Mason, WA interconnection queue

2 active projects totalling 202 MW in the BPA queue, plus 3 with terminal status (shown greyed).

2active projects
202active MW
5total filed
Queue IDProjectkVMWResourceStatus
G0973 Not reported 230 300 Wind WITHDRAWN
G1048 Not reported 230 200 Solar STUDY
G0378 Not reported n/r 65 Other WITHDRAWN
G0426 Not reported n/r 31 Other WITHDRAWN
G0498 Lilliwaup Falls Hydro Project n/r 2 Hydro ENERGIZED

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.