Queue request 423 was listed in the TVA interconnection queue at the end of 2025 as a 200 MW solar project in Clay County, MS, according to Berkeley Lab’s queue data file. The filing names West Point 161-kV Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of January 31, 2026.

Queue ID423
Project nameNot reported
Status (as published)Active
SubstationWest Point 161-kV Substation
Point of interconnectionWest Point 161-kV Substation
CountyClay
StateMS
VoltageNot reported
Capacity200 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-01-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

West Point 161-kV Substation substation: 3 requests in the TVA queue, 3 active totaling 450 MW.

Queue IDProjectMWResourceStatus
429Not reported200BatteryActive
424Not reported50BatteryActive

Clay, MS: 16 requests in the TVA queue, 5 active totaling 850 MW.

Tracked changes

Not tracked. TVA rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityTennessee Valley Authority
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2020-04-21

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first