Substation Scout

West Point 161-kV Substation substation interconnection queue

3 active projects totaling 450 MW in the TVA queue.

3 TVA queue filings name West Point 161-kV Substation as the point of interconnection, all in Clay County, MS.

3active projects
450active MW
3total filed
Queue IDProjectkVMWResourceStatus
423 Not reported n/r 200 Solar Active
429 Not reported n/r 200 Battery Active
424 Not reported n/r 50 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with TVA before relying on these figures.