Sporn

Named in 2 PJM planning documents for 2 projects, from December 3, 2024 to January 7, 2025.

Not stateddescribed as
OVECzone
345VkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Kyger Creek Upgrades
B3899.1
Not printed $0.8 M 4/1/2029 Not printed 2025-01-07
TEAC
Kyger Creek Upgrades Not printed $0.8 M 4/1/2029 Not printed 2024-12-03
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 37
Kyger Creek Upgrades No role wording
345V
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 59
Kyger Creek Upgrades No role wording
345V

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.