Nye, NV interconnection queue
6 active projects totaling 2,915 MW in the NV Energy queue, plus 16 with terminal status (shown grayed).
6active projects
2,915active MW
22total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| Company 238 | Not reported | n/r | 1,000 | Hybrid | Active |
| Company 240 | Not reported | n/r | 1,000 | Hybrid | Withdrawn |
| Company 236 | Not reported | n/r | 600 | Hybrid | Withdrawn |
| Company 245 | Not reported | n/r | 600 | Hybrid | Withdrawn |
| Company 254 | Not reported | n/r | 600 | Hybrid | Active |
| Company 255 | Not reported | n/r | 600 | Hybrid | Active |
| Company 234 | Not reported | n/r | 540 | Hybrid | Withdrawn |
| Company 239 | Not reported | n/r | 500 | Hybrid | Withdrawn |
| Company 247 | Not reported | n/r | 500 | Hybrid | Withdrawn |
| Company 256 | Not reported | n/r | 500 | Hybrid | Active |
| Company 259 | Not reported | n/r | 500 | Hybrid | Withdrawn |
| Company 246 | Not reported | n/r | 400 | Hybrid | Withdrawn |
| Company 235 | Not reported | n/r | 370 | Hybrid | Withdrawn |
| Company 244 | Not reported | n/r | 308 | Wind | Withdrawn |
| 25-00403 | Not reported | n/r | 199 | Hybrid | Active |
| Company HI | Not reported | n/r | 100 | Solar | Withdrawn |
| Company KM | Not reported | n/r | 100 | Hybrid | Withdrawn |
| Company MO | Not reported | n/r | 100 | Hybrid | Withdrawn |
| Company GE | Not reported | n/r | 50 | Solar | Withdrawn |
| Company GF | Not reported | n/r | 20 | Solar | Withdrawn |
| 25N-SG7 | Not reported | n/r | 16 | Other | Active |
| Company QZ | Not reported | n/r | 10 | Other | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with NV Energy before relying on these figures.
Site Scanner