Orinoco
In a case before the Kentucky Public Service Commission, “Belfry Area Transmission Line Project” (case 2023-00040). The station's utility: Kentucky Power.
Described as new. The quoted wording describes building this substation, without the word "new". “Construct Orinoco 69 kV Substation in Pike County, Kentucky” — Commission final order, Case 2023-00040, p.1 (case 2023-00040)
Also mentioned: “Construct Orinoco 69 kV Substation in Pike County, Kentucky” — Commission final order, Case 2022-00236, p.2 (case 2022-00236)
Note. The order says Orinoco will replace the existing Belfry 46 kV Substation, on a 6.5-mile 69 kV line between the existing New Camp and Stone 69 kV substations.
Note. Kentucky Power first applied in Case 2022-00236; that application was denied without prejudice on 2023-01-05. The refiled application (Case 2023-00040) was granted a CPCN on 2023-10-06. Neither case record read here says whether Orinoco has been built.
County: “Construct Orinoco 69 kV Substation in Pike County, Kentucky” — Commission final order, Case 2023-00040, p.1 (case 2023-00040).
Generation interconnection requests filed in Pike, KY: PJM queue, 2 active of 10. Same county, not the same substation.
Source: Kentucky Public Service Commission case records (psc.ky.gov): 36 transmission and substation cases filed since 2022 read by hand, 20 documents cited. Latest document dated November 13, 2026; retrieved 2026-11-21; records reviewed by hand 2026-11-21.
Before relying on any of this
- These are the substations named in Kentucky Public Service Commission cases since 2022: a utility files for a certificate when it builds most new transmission. Smaller substations, and projects that need no certificate, are not in these cases.
- A county is shown where the case prints it for the station; otherwise it is left blank.
- An application describes what a utility asks to build. Where the Commission has ruled, the page says so; an in-service date is the one the documents print, not a construction schedule.