Henry Clay
In a case before the Kentucky Public Service Commission, “Breaks-Dorton Project (46kV to 69kV conversion)” (case 2026-00184). The station's utility: Kentucky Power.
Expansion at an existing substation: new voltage level. The quoted wording describes a yard, bus or conversion at a voltage this substation is not otherwise shown at. “Rebuild the Henry Clay Substation to 69kV standards.” — Kentucky Power application, Case 2026-00184, p.5 (case 2026-00184)
Existing station: The application describes Henry Clay today as a single 46/34.5kV yard; 69kV is a voltage the station does not have. “The Henry Clay Substation consists of one 46/34.5kV yard.” — Kentucky Power application, Case 2026-00184, p.3 (case 2026-00184)
Note. The Koehler testimony says the project changed after it was presented at PJM: instead of replacing Henry Clay with a new Poor Bottom Substation, Henry Clay will be expanded and rebuilt on its existing property.
Note. Pending as of 2026-11-21: filed 2026-09-11, no final order.
County: “The existing Henry Clay Substation, and its associated Henry Clay Switching Station, was originally built in 1987 and are located in Pike County, Kentucky.” — Kentucky Power application, Case 2026-00184, p.3 (case 2026-00184).
Generation interconnection requests filed in Pike, KY: PJM queue, 2 active of 10. Same county, not the same substation.
Source: Kentucky Public Service Commission case records (psc.ky.gov): 36 transmission and substation cases filed since 2022 read by hand, 20 documents cited. Latest document dated November 13, 2026; retrieved 2026-11-21; records reviewed by hand 2026-11-21.
Before relying on any of this
- These are the substations named in Kentucky Public Service Commission cases since 2022: a utility files for a certificate when it builds most new transmission. Smaller substations, and projects that need no certificate, are not in these cases.
- A county is shown where the case prints it for the station; otherwise it is left blank.
- An application describes what a utility asks to build. Where the Commission has ruled, the page says so; an in-service date is the one the documents print, not a construction schedule.