Buzzard Roost
Named in 6 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
6projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| ADAMSVILLE - BUZZARD ROOST 230kV REBUILD AND JUMPER UPGRADE Rebuild the line sections from Adamsville to Boat Rock Road (7.2 miles) on the Adamsville - Buzzard Roost 230kV line with 200C 1351 ACSS Martin conductor. Replace the limiting jumpers on the line at Adamsville, Bakers Ferry, and Boat Rock with higher rated jumpers. Replace limiting line switches at Boat Rock with higher rated switches. TEAMS 19597 · plan p.85 · zone 208 |
GPC | In the plan p.7 |
Jun 1, 2026 | No change | Adamsville, Buzzard Roost |
| GTC: ADAMSVILLE - BUZZARD ROOST 230kV REBUILD Rebuild approximately 5 miles of the Adamsville - Buzzard Roost 230kV line with 200C 1351 ACSS Martin. TEAMS 20858 · plan p.126 · zone 201 |
GTC | In the plan p.10 |
Jun 1, 2027 | No change | Adamsville, Buzzard Roost |
| BUZZARD ROOST - FACTORY SHOALS 230kV NEW LINE Build 2 miles of new 230kV line from Buzzard Roost to Factory Shoals with 200C 1351 ACSS Martin. TEAMS 21036 · plan p.193 · zone 201 |
GPC | In the plan p.15 |
Jun 1, 2029 | No change | Buzzard Roost, FACTORY SHOALS |
| BUZZARD ROOST - TRIBUTARY 230kV REBUILD Rebuild the 2.8 miles Tributary - Thornton Road 230kV line with 200C 1351 ACSS Martin. TEAMS 21098 · plan p.234 · zone 201 |
GPC | In the plan p.17 |
Jun 1, 2030 | No change | Buzzard Roost, Thornton Road, Tributary |
| GTC: BUZZARD ROOST - THORNTON ROAD 230kV REBUILD Rebuild the Buzzard Roost - Thornton Road 230kV line, approximately 1 mile, with 200C 1351 ACSS conductor. TEAMS 21610 · plan p.204 · zone 201 |
GTC | In the plan p.15 |
Jun 1, 2029 | New project | Buzzard Roost, Thornton Road |
| GTC: BUZZARD ROOST – ROCKHOUSE RD 230kV REBUILD Rebuild the Buzzard Roost – Rockhouse Road 230kV line circuit 2, approximately 0.81 mile, with 200C 1351 ACSS conductor. TEAMS 21620 · plan p.245 · zone 201 |
GTC | In the plan p.18 |
Jun 1, 2030 | New project | Buzzard Roost, ROCKHOUSE RD, Rockhouse Road |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.
Site Scanner