Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Williamson County. First named in the release with data as of October 1, 2022.

Williamsoncounty as printed
138kV
LCRATSCutility
2projects listed

Also printed as: Georgetown Substation

A HIFLD substation record has the same name and county: GEORGETOWN (WILLIAMSON County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Williamson, TX: ERCOT queue, 1 active of 3. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Chief Brady - Georgetown Transmission Line Upgrade
LCRA TSC will upgrade T355 Chief Brady - Georgetown 138-kV transmission line to achieve a higher operational rating.
ERCOT project 70922 · RTP 2023-SC17
LCRATSC
Tier 4
Planned
Completed tab
138 Apr 2025
actual 2025-04
Chief Brady to Georgetown
Williamson County
Chief Brady, Georgetown
Georgetown - Rivery Transmission Line Upgrade
LCRA TSC will upgrade T597 Georgetown - Rivery 138-kV transmission line to achieve a higher operational rating.
ERCOT project 85973 · RTP 2023-SC17
LCRATSC
Tier 4
Planned
Current-year planned tab
138 Dec 2026 Georgetown Substation
Williamson County
Georgetown Substation

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202685973Moved between tabsFuture → Current-year planned
October 1, 202585973Projected in-service dateMay 2026 → Dec 2026
June 1, 202570922Moved between tabsFuture → Completed
February 1, 202570922Projected in-service dateMay 2025 → Apr 2025
October 1, 202470922Projected in-service dateApr 2025 → May 2025
October 1, 202485973First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.