Bent Tree Substation

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Williamson County. First named in the release with data as of June 1, 2025.

Williamsoncounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Williamson, TX: ERCOT queue, 1 active of 3. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Bent Tree 138 kV Substation
Establish Bent Tree 138 kV Substation with 55.2 MVAR capacitor bank using 3-18.4 MVAR stages
ERCOT project 93191 · utility no. R6388
ONCOR
Tier 4
Planned
Future tab
138 May 2027 Bent Tree Substation to Bent Tree Substation
Williamson County
Bent Tree Substation

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202693191Moved between tabsCurrent-year planned → Future
October 1, 202693191Projected in-service dateDec 2026 → May 2027
February 1, 202693191Moved between tabsFuture → Current-year planned
February 1, 202693191Projected in-service dateMay 2026 → Dec 2026
June 1, 202593191First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.