El Campo
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Wharton County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.
Whartoncounty as printed
69, 138kV
AEP TCC, STECutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Wharton, TX: ERCOT queue, 42 active of 44. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| El Campo to Corichi: Rebuild 138 kV Line Rehab the El Campo to Corichi 138 kV line ERCOT project 70796 · utility no. TA2018020 |
AEP TCC Tier 4 |
Planned Future tab |
138 | May 2029 | El Campo to Corichi Wharton County |
El Campo, Corichi |
| Rebuild Nada to El Campo 69 kV line Rebuild Nada to El Campo 69 kV line from 4/0 to 795. 2023 RTP ERCOT project 78483 |
STEC Tier 4 |
Under Construction Current-year planned tab |
69 | Sep 2026 | Nada to El Campo Colorado / Wharton County |
Nada, El Campo |
On the Cancelled tab
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Texana Solar Interconnection Connect the Texana Solar to the El Campo to Victoria 138 kV line ERCOT project 64021 · utility no. TP2020888 |
AEP TCC Tier 4 |
Planned Cancelled tab |
138 | Jun 2025 | El Campo to Victoria Wharton / Victoria County |
El Campo, Victoria |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 78483 | Status as reported | Planned → Under Construction |
| October 1, 2026 | 78483 | Projected in-service date | Jul 2026 → Sep 2026 |
| July 13, 2026 | 78483 | Projected in-service date | May 2026 → Jul 2026 |
| February 1, 2026 | 78483 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 64021 | Projected in-service date | Jan 2025 → Jun 2025 |
| February 1, 2025 | 64021 | Projected in-service date | Sep 2024 → Jan 2025 |
| February 1, 2025 | 78483 | Status as reported | Conceptual → Planned |
| October 1, 2024 | 70796 | Projected in-service date | May 2028 → May 2029 |
| October 1, 2024 | 78483 | Projected in-service date | Dec 2025 → May 2026 |
| June 1, 2024 | 64021 | Moved between tabs | Future → Cancelled |
| June 1, 2024 | 70796 | Projected in-service date | May 2027 → May 2028 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.