Nada

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Colorado County. First named in the release with data as of February 1, 2015.

Coloradocounty as printed
69kV
STECutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Colorado, TX: ERCOT queue, 14 active of 16. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rebuild Nada to El Campo 69 kV line
Rebuild Nada to El Campo 69 kV line from 4/0 to 795. 2023 RTP
ERCOT project 78483
STEC
Tier 4
Under Construction
Current-year planned tab
69 Sep 2026 Nada to El Campo
Colorado / Wharton County
Nada, El Campo

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202678483Status as reportedPlanned → Under Construction
October 1, 202678483Projected in-service dateJul 2026 → Sep 2026
July 13, 202678483Projected in-service dateMay 2026 → Jul 2026
February 1, 202678483Moved between tabsFuture → Current-year planned
February 1, 202578483Status as reportedConceptual → Planned
October 1, 202478483Projected in-service dateDec 2025 → May 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.