Corichi

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Wharton County. First named in the release with data as of February 1, 2020.

Whartoncounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Wharton, TX: ERCOT queue, 42 active of 44. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
El Campo to Corichi: Rebuild 138 kV Line
Rehab the El Campo to Corichi 138 kV line
ERCOT project 70796 · utility no. TA2018020
AEP TCC
Tier 4
Planned
Future tab
138 May 2029 El Campo to Corichi
Wharton County
El Campo, Corichi

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202470796Projected in-service dateMay 2028 → May 2029
June 1, 202470796Projected in-service dateMay 2027 → May 2028

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.