Wolf
Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Ward County. First named in the release with data as of June 1, 2016.
Wardcounty as printed
138kV
ONCORutility
4projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Ward, TX: ERCOT queue, 12 active of 13. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Pecos Trail to Wolf 138 kV Line Section Rebuild Rebuild the existing 138 kV line section from Pecos Trail to Wolf 138 kV. ERCOT project 104158 · utility no. R8527 · RPG 25RPG008 |
ONCOR Tier 3 |
Planned Future tab |
138 | Dec 2028 | Pecos Trail to Wolf Ward County |
Pecos Trail, Wolf |
| Edwards Tap - Sandhills Tap 138 kV Line Rebuild ERCOT project 81383 · utility no. R8528 |
ONCOR Tier 3 |
In-Service Completed tab |
138 | May 2025 actual 2025-07 |
Odessa EHV to Wolf Ector / Ward County |
Odessa EHV, Wolf |
| Sandhills Tap - Wolf 138 kV Line Rebuild ERCOT project 81389 · utility no. R8528 |
ONCOR Tier 3 |
Planned Completed tab |
138 | Dec 2025 actual 2025-12 |
Odessa EHV to Wolf Ector / Ward County |
Odessa EHV, Wolf |
| Yarbrough - Pecos Trail 138 kV Line Section Rebuild Rebuild the existing 138 kV line section from Yarbrough - Pecos Trail POD 138 kV. ERCOT project 81440 · utility no. R8527 · RPG 25RPG008 |
ONCOR Tier 3 |
Planned Future tab |
138 | Sep 2027 | Wolf to Yarbrough Ward / Ector County |
Wolf, Yarbrough |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2026 | 104158 | First listed | on the Future tab |
| June 1, 2026 | 81440 | Projected in-service date | May 2027 → Sep 2027 |
| February 1, 2026 | 81383 | Status as reported | Planned → In-Service |
| February 1, 2026 | 81389 | Moved between tabs | Current-year planned → Completed |
| June 1, 2025 | 81383 | Moved between tabs | Future → Completed |
| June 1, 2025 | 81389 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 81440 | Projected in-service date | Dec 2027 → May 2027 |
| June 1, 2024 | 81383 | First listed | on the Future tab |
| June 1, 2024 | 81389 | First listed | on the Future tab |
| June 1, 2024 | 81440 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.