Substation Scout

Rock Draw

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Ward County. First named in the release with data as of October 1, 2026.

Wardcounty as printed
138kV
TNMPutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Ward, TX: ERCOT queue, 12 active of 13. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Silverleaf 138kV station from TNMP submitted Cowpen/Silverleaf RPG
Construct TNMP Silverleaf 345kV-138kV BAAH substation. Install three 750 MVA 345kV-138kV transformers. Cut both Pecos to Cedarvale 138kV lines and Bone Springs Tap 138kV line into Silverleaf 138kV bus. Construct three 345kV tie lines from TNMP Silverleaf 345kV to Oncor Rock Draw 345kV Switching Station (PMCR # 78044).
ERCOT project 77807A · RPG 23RPG013
TNMP
Tier 1
Under Construction
Current-year planned tab
138 Dec 2026 No terminals printed
Ward County
Silverleaf, BAAH, Rock Draw, Pecos, Cedarvale

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202677807AFirst listedon the Current-year planned tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first