Substation Scout

Riverton

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Ward County. First named in the release with data as of October 1, 2024.

Wardcounty as printed
345kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Ward, TX: ERCOT queue, 12 active of 13. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Riverton - Sandlake 138 kV Line Conversion 345 kV and Riverton - Sandlake 138 kV Line
Convert Riverton – Sandlake 138 kV Line to 345 kV and Establish Riverton – Sandlake 138 kV Line
ERCOT project 87017 · utility no. R8793 · RPG 24RPG010
ONCOR
Tier 1
Planned
Current-year planned tab
345 Dec 2026 Riverton to Sandlake
Ward / Reeves County
Riverton, Sandlake

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202687017Moved between tabsFuture → Current-year planned
October 1, 202487017First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.