Pyote

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Ward County, plus 1 on its Cancelled tab. First named in the release with data as of June 1, 2019.

Wardcounty as printed
138kV
TNMPutility
1projects listed

A HIFLD substation record has the same name and county: PYOTE (WARD County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Ward, TX: ERCOT queue, 12 active of 13. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Reconfigure TNMP Pyote 138kV Substation.
ERCOT project 87423
TNMP
Tier 4
Planned
Future tab
138 May 2027 No terminals printed
Ward County
Pyote

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Double circuit 138kV tie between Pyote and Coyanosa
Project resubmitted as PMCR ID # 77805
ERCOT project 70943
TNMP
Tier 2
Conceptual
Cancelled tab
138 Jun 2025 Pyote (bus # 38001) to Coyanosa (bus # 38380)
Ward / Reeves County
Pyote, Coyanosa

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202687423Projected in-service dateDec 2026 → May 2027
October 1, 202470943Moved between tabsFuture → Cancelled
October 1, 202487423First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.