Rayburn

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Victoria County. First named in the release with data as of February 1, 2024.

Victoriacounty as printed
138kV
STECutility
3projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Victoria, TX: ERCOT queue, 17 active of 22. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade Victoria-Rayburn
Upgrade Victoria- Loop 463- Rayburn to 403 MVA
ERCOT project 76788
STEC
Tier 4
Planned
Current-year planned tab
138 Mar 2026 Rayburn to Victoria
Victoria County
Rayburn, Victoria
Upgrade Rayburn Auto Station
Upgrade Rayburn Auto
ERCOT project 76818
STEC
Tier 4
Planned
Future tab
138 Jul 2029 Rayburn to Rayburn
Victoria County
Rayburn
New Furhman Substation
Adds New Furhman switching station on Rayburn - Vanderbilt line for generator interconnect
ERCOT project 82829
STEC
Tier 4
In-Service
Completed tab
138 Jul 2025
actual 2025-08
Rayburn to Vanderbilt
Victoria County
Rayburn, Vanderbilt

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202676788Projected in-service dateDec 2026 → Mar 2026
October 1, 202682829Moved between tabsCurrent-year planned → Completed
October 1, 202682829Status as reportedPlanned → In-Service
February 1, 202676788Moved between tabsFuture → Current-year planned
February 1, 202676818Projected in-service dateMay 2028 → Jul 2029
October 1, 202576788Moved between tabsCurrent-year planned → Future
October 1, 202576788Projected in-service dateDec 2025 → Dec 2026
October 1, 202576818Projected in-service dateOct 2026 → May 2028
October 1, 202582829Projected in-service dateApr 2025 → Jul 2025
June 1, 202576788Moved between tabsFuture → Current-year planned
June 1, 202582829Moved between tabsFuture → Current-year planned
February 1, 202582829Projected in-service dateFeb 2025 → Apr 2025
October 1, 202476818First listedon the Future tab
June 1, 202482829First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.