Nameless

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Travis County. First named in the release with data as of June 1, 2021.

Traviscounty as printed
138kV
PECutility
3projects listed

A HIFLD substation record has the same name and county: NAMELESS (TRAVIS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Travis, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Lago Vista to Nameless Transmission Line Upgrade
Rebuild and upgrade Nameless to Lago Vista with double-circuit capable structures. Install 1 ckt with bundled 795 kcmil conductor (440 MVA). Final span of conductor and terminal equipment at Nameless will be upgraded to 440 MVA with ERCOT project #72576B. (Replaces ERCOT Project # 61277A)
ERCOT project 72576A
PEC
Tier 4
Planned
Completed tab
138 Apr 2025
actual 2025-04
Lago Vista to Nameless
Travis County
Lago Vista, Nameless
Lago Vista to Nameless Transmission Line Upgrade
Upgrade final span into Nameless, upgrade terminal equipment, and achieve circuit rating of 440 MVA. (Replaces ERCOT Project #61277B)
ERCOT project 72576B
PEC
Tier 4
Planned
Current-year planned tab
138 Jul 2026 Lago Vista to Nameless
Travis County
Lago Vista, Nameless
Nameless to Leander Transmission Line Upgrade
Upgrade final span into Nameless, upgrade terminal equipment, and achieve circuit rating of 440 MVA. (Replaces ERCOT Project # 61279C)
ERCOT project 72582C
PEC
Tier 4
Planned
Completed tab
138 Jul 2026
actual 2026-05
Hero Way to Nameless
Travis County
Hero Way, Nameless

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202672576BProjected in-service dateMay 2026 → Jul 2026
July 13, 202672582CProjected in-service dateMay 2026 → Jul 2026
June 1, 202672582CMoved between tabsCurrent-year planned → Completed
February 1, 202672576BMoved between tabsFuture → Current-year planned
February 1, 202672582CMoved between tabsFuture → Current-year planned
June 1, 202572576AMoved between tabsFuture → Completed
October 1, 202472576BProjected in-service dateJan 2026 → May 2026
October 1, 202472582CProjected in-service dateJan 2026 → May 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.