Nameless
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Travis County. First named in the release with data as of June 1, 2021.
A HIFLD substation record has the same name and county: NAMELESS (TRAVIS County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Travis, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Lago Vista to Nameless Transmission Line Upgrade Rebuild and upgrade Nameless to Lago Vista with double-circuit capable structures. Install 1 ckt with bundled 795 kcmil conductor (440 MVA). Final span of conductor and terminal equipment at Nameless will be upgraded to 440 MVA with ERCOT project #72576B. (Replaces ERCOT Project # 61277A) ERCOT project 72576A |
PEC Tier 4 |
Planned Completed tab |
138 | Apr 2025 actual 2025-04 |
Lago Vista to Nameless Travis County |
Lago Vista, Nameless |
| Lago Vista to Nameless Transmission Line Upgrade Upgrade final span into Nameless, upgrade terminal equipment, and achieve circuit rating of 440 MVA. (Replaces ERCOT Project #61277B) ERCOT project 72576B |
PEC Tier 4 |
Planned Current-year planned tab |
138 | Jul 2026 | Lago Vista to Nameless Travis County |
Lago Vista, Nameless |
| Nameless to Leander Transmission Line Upgrade Upgrade final span into Nameless, upgrade terminal equipment, and achieve circuit rating of 440 MVA. (Replaces ERCOT Project # 61279C) ERCOT project 72582C |
PEC Tier 4 |
Planned Completed tab |
138 | Jul 2026 actual 2026-05 |
Hero Way to Nameless Travis County |
Hero Way, Nameless |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 72576B | Projected in-service date | May 2026 → Jul 2026 |
| July 13, 2026 | 72582C | Projected in-service date | May 2026 → Jul 2026 |
| June 1, 2026 | 72582C | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 72576B | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 72582C | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 72576A | Moved between tabs | Future → Completed |
| October 1, 2024 | 72576B | Projected in-service date | Jan 2026 → May 2026 |
| October 1, 2024 | 72582C | Projected in-service date | Jan 2026 → May 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.