Mag Plant Substation

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Travis County. First named in the release with data as of February 1, 2015.

Traviscounty as printed
138kV
AENutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Travis, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Northland to Mag Plant Circuit 979 Upgrade
Reconductor the existing Northland to Mag Plant circuit from single 795SCAR to bundle 795 ACSR Drake and increase rating to 3000 Amp
ERCOT project 14TPIT0038 · utility no. NEW
AEN
Tier 4
Planned
Future tab
138 Jun 2028 Northland Substation to Mag Plant Substation
Travis County
Northland Substation, Mag Plant Substation
McNeil to MagPlant Ckt 977 Upgrade
Reconductor existing McNeil to MagPlant circuit from 2000 to 3000 Amp. Relocate McNeil to Summit Circuit 907 and McNeil to MagPlant Circuit 977 to separate structures. Kramer Lane (KA) substation will be cut-into this line in 2023
ERCOT project 16TPIT0007 · utility no. P396
AEN
Tier 4
Planned
Future tab
138 Jun 2030 McNeil Substation to Mag Plant Substation
Travis County
McNeil Substation, Mag Plant Substation

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202514TPIT0038Projected in-service dateJun 2025 → Jun 2028
June 1, 202516TPIT0007Projected in-service dateJun 2025 → Jun 2030
October 1, 202416TPIT0007Moved between tabsCompleted → Future
October 1, 202416TPIT0007Projected in-service dateJun 2024 → Jun 2025
June 1, 202416TPIT0007Moved between tabsFuture → Completed

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.