Austrop
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Travis County. First named in the release with data as of February 1, 2015.
A HIFLD substation record has the same name and county: AUSTROP (TRAVIS County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Travis, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Austrop Bus Substation Upgrade Upgrade terminal equipment of Austrop (Bus #9328) to increase operational rating of terminating 138-kV lines to 643 MVA. Upgrade project for Batch Zero Base Load ERCOT project 110164 |
LCRATSC Tier 4 |
Conceptual Future tab |
138 | Dec 2029 | Austrop Travis County |
Austrop |
| Austrop - Sim Gideon Transmission Line Upgrade Upgrade the Austrop - Sim Gideon 138-kV double-circuit transmission line, including lines connecting to Bastrop City and Webberville, to achieve a minimum 560 MVA emergency rating for all lines in series at the Austrop, Webberville, Sim Gideon, Settlers, and Bastrop City substations. Ideally, lines will be rated to 4000A. This is an LCP Upgrade project to support Batch Zero Base Load ERCOT project 110185 |
LCRATSC Tier 4 |
Conceptual Future tab |
138 | Dec 2028 | Austrop to Sim Gideon Travis / Bastrop County |
Austrop, Sim Gideon |
| Austrop - Sim Gideon Transmission Line Upgrade LCRA TSC will upgrade the Austrop - Sim Gideon 138-kV double-circuit transmission line to achieve a higher operational rating. This line consists of the following transmission circuits. T171 Austrop - Sim Gideon T172 Bastrop City - Sim Gideon (via Settlers) T231 Bastrop City - Webberville (via Settlers) T673 Austrop - Webberville ERCOT project 91487 · utility no. PLC-8100 |
LCRATSC Tier 3 |
Planned Future tab |
138 | Dec 2028 | Austrop to Sim Gideon Travis / Bastrop County |
Austrop, Sim Gideon |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 110164 | Projected in-service date | Dec 2030 → Dec 2029 |
| July 13, 2026 | 110164 | First listed | on the Future tab |
| July 13, 2026 | 110185 | First listed | on the Future tab |
| July 13, 2026 | 91487 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.