San Angelo Concho

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Tom Green County. First named in the release with data as of June 1, 2024.

Tom Greencounty as printed
69kV
AEP TNCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Tom Green, TX: ERCOT queue, 13 active of 13. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Ballinger to Concho: Rebuild 69 kV line
Rebuild Ballinger to Concho 69 kV line, install POP switch for Rowena, install CB at Miles, install POP switch for Harriett REA
ERCOT project 55421 · utility no. 1861 · RPG 20RPG004
AEP TNC
Tier 3
Under Construction
Future tab
69 Oct 2027 Ballinger to San Angelo Concho
Runnels / Tom Green County
Ballinger, San Angelo Concho

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202655421Status as reportedPlanned → Under Construction
June 1, 202655421Projected in-service dateMay 2027 → Oct 2027
February 1, 202555421Projected in-service dateDec 2026 → May 2027
June 1, 202455421Projected in-service dateMay 2025 → Dec 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.