Snodgrass

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Taylor County. First named in the release with data as of June 1, 2024.

Taylorcounty as printed
69kV
GSECutility
1projects listed

Described as new. The quoted wording calls this substation new. “new Snodgrass sub” — project 81354 description, as the utility reported it

Reported complete. Project 81354 is on the Completed tab (actual in-service 2025-04), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Taylor, TX: ERCOT queue, 13 active of 15. Same county, not the same substation.

Location

32.2376, -99.7764 · Taylor County, TX · view on a map

OpenStreetMap, corroborated. An OpenStreetMap feature carries this exact name, and a cited source agrees. Accurate to about ±100 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: Centroid of OpenStreetMap way 1392720326 'Snodgrass Substation' (operator Golden Spread Electric Cooperative), about 14 km south of OSM Abilene South Substation. Corroborated: TPIT 81354 names GSEC as the TSP for the new Snodgrass sub, and the OSM yard sits beside OSM 69 kV line way 7840034, which runs south from the Abilene South area, consistent with TPIT's 'Abilene South to Steamboat 69 kV line'. +/- ~100 m (yard footprint).

Note: OSM tags the yard voltage 138000; TPIT models Snodgrass at 69 kV on a 69 kV line. Location not affected.

County: the Census county at this point.

Sources: ERCOT TPIT, projects 81354 and 76139 (release 2026-10-01), Completed tab · OpenStreetMap: Snodgrass Substation (GSEC) (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
GSEC_9452_Add_Snodgrass_Sub
Adding new Snodgrass sub to connect to AEP's Juncus Station.
ERCOT project 81354
GSEC
Tier 4
In-Service
Completed tab
69 Apr 2025
actual 2025-04
No terminals printed
Taylor County
Snodgrass, Juncus

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202681354Moved between tabsCurrent-year planned → Completed
October 1, 202681354Status as reportedPlanned → In-Service
June 1, 202581354Moved between tabsFuture → Current-year planned
June 1, 202481354First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.