Sonora
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Sutton County. First named in the release with data as of June 1, 2017.
Suttoncounty as printed
69kV
AEP TNC, AEP TNC/AEP TCCutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Sutton, TX: ERCOT queue, 2 active of 3. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Eldorado Live Oak to Sonora: Rebuild 69 kV line Rehab Eldorado Live Oak to Sonora 69 kV line ERCOT project 45501 · utility no. 2769 · RPG 18RPG012 |
AEP TNC Tier 3 |
In-Service Completed tab |
69 | Mar 2025 actual 2025-03 |
Eldorado Live Oak to Sonora Schleicher / Sutton County |
Eldorado Live Oak, Sonora |
| Friess Ranch to Sonora: Rebuild 69 kV line Rehab Rocksprings to Sonora 69 kV line ERCOT project 51001 · utility no. 2791 · RPG 19RPG018 |
AEP TNC/AEP TCC Tier 3 |
Planned Future tab |
69 | Jan 2029 | Friess Ranch to Sonora Sutton County |
Friess Ranch, Sonora |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2026 | 51001 | Projected in-service date | Apr 2028 → Jan 2029 |
| June 1, 2025 | 45501 | Moved between tabs | Future → Completed |
| June 1, 2025 | 45501 | Status as reported | Planned → In-Service |
| June 1, 2025 | 45501 | Projected in-service date | Feb 2025 → Mar 2025 |
| June 1, 2024 | 45501 | Projected in-service date | Dec 2024 → Feb 2025 |
| June 1, 2024 | 51001 | Projected in-service date | Apr 2026 → Apr 2028 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.