Substation Scout

Sutton, TX interconnection queue

2 active projects totalling 307.1 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

2active projects
307.1active MW
3total filed
Queue IDProjectkVMWResourceStatus
28INR0113 Axis Ridge Wind 138 392 Wind Cancelled
28INR0148 Sonora High Noon BESS 138 204.1 Battery SS Completed, FIS Started, No IA
27INR0236 Atticus Energy Storage 69 103 Battery SS Completed, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.