Substation Scout

Eldorado Live Oak

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Schleicher County. First named in the release with data as of June 1, 2017.

Schleichercounty as printed
69kV
AEP TNCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Schleicher, TX: ERCOT queue, 10 active of 12. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Eldorado Live Oak to Sonora: Rebuild 69 kV line
Rehab Eldorado Live Oak to Sonora 69 kV line
ERCOT project 45501 · utility no. 2769 · RPG 18RPG012
AEP TNC
Tier 3
In-Service
Completed tab
69 Mar 2025
actual 2025-03
Eldorado Live Oak to Sonora
Schleicher / Sutton County
Eldorado Live Oak, Sonora

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202545501Moved between tabsFuture → Completed
June 1, 202545501Status as reportedPlanned → In-Service
June 1, 202545501Projected in-service dateFeb 2025 → Mar 2025
June 1, 202445501Projected in-service dateDec 2024 → Feb 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.