Union
Named in 8 listed projects in ERCOT’s transmission project tracking workbook, in Scurry County. First named in the release with data as of October 1, 2025.
Scurrycounty as printed
138kV
ONCORutility
8projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Scurry, TX: ERCOT queue, 17 active of 23. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Union 138 kV Switch Establish Union 138 kV Switch ERCOT project 102849A · utility no. R8608 |
ONCOR Tier 4 |
Planned Current-year planned tab |
138 | Dec 2026 | Union to Union Scurry County |
Union |
| Union 138 kV Switch Cut-in the Deep Creek - Sacroc 138 kV Line Section into Union 138 kV Switch ERCOT project 102849B · utility no. R8608 |
ONCOR Tier 4 |
Planned Future tab |
138 | Dec 2027 | Union to Union Scurry County |
Union |
| Union - Deep Creek 138 kV Line Rebuild Rebuild existing 138 kV line ERCOT project 105060 · utility no. R8744 · RPG 26RPG014 |
ONCOR Tier 3 |
Planned Future tab |
138 | May 2027 | Union to Deep Creek Scurry County |
Union, Deep Creek |
| Union - Dermott 138 kV Line Rebuild Rebuild existing 138 kV Line ERCOT project 105063 · utility no. R8839 · RPG 26RPG014 |
ONCOR Tier 3 |
Planned Future tab |
138 | May 2027 | Union to Dermott Scurry County |
Union, Dermott |
| Stoplight (fka Bluff Creek) - Union 138 kV Line Rebuild Rebuild the existing Stoplight (fka Bluff Creek) - Union 138 kV Line Rebuild ERCOT project 87653 · utility no. R9002 · RPG 26RPG014 |
ONCOR Tier 3 |
Planned Current-year planned tab |
138 | Dec 2026 | Stoplight (fka Bluff Creek) to Union Scurry County |
Stoplight (fka Bluff Creek), Union |
| Union (fka Sun) - Golden Switch - Dermott 138 kV line Rebuild Add Permian Basin Reliability Plan Upgrade ID L22C. Upgrade the existing Union (fka Sun) - Golden Switch - Dermott 138-kV line ERCOT project 99369 · utility no. PB_L22_C |
ONCOR Tier 3 |
Planned Future tab |
138 | Jun 2027 | Union to Dermott Scurry County |
Union, Dermott |
| Sun - Sacroc - Union 138 kV Line Rebuild Add Permian Basin Reliability Plan Upgrade ID L22D. Upgrade the existing Sun - Sacroc - Union 138 kV Line Rebuild. ERCOT project 99407 · utility no. PB_L22_D |
ONCOR Tier 4 |
Planned Future tab |
138 | Dec 2027 | Sun to Union Scurry County |
Sun, Union |
| Union (fka Sun) - Ranger Camp 138 kV Line Rebuild Add Permian Basin Reliability Plan Upgrade ID L22B. Upgrade the existing Union (fka Sun) - Ranger Camp 138-kV line. ERCOT project 99520 · utility no. PB_L22_B |
ONCOR Tier 3 |
Planned Future tab |
138 | Jun 2028 | Union to Dermott Scurry County |
Union, Dermott |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2026 | 102849A | First listed | on the Current-year planned tab |
| June 1, 2026 | 102849B | First listed | on the Future tab |
| June 1, 2026 | 105060 | First listed | on the Future tab |
| June 1, 2026 | 105063 | First listed | on the Future tab |
| February 1, 2026 | 87653 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 87653 | Projected in-service date | May 2032 → Dec 2026 |
| October 1, 2025 | 99369 | First listed | on the Future tab |
| October 1, 2025 | 99407 | First listed | on the Future tab |
| October 1, 2025 | 99520 | First listed | on the Future tab |
| June 1, 2025 | 87653 | Projected in-service date | Dec 2026 → May 2032 |
| October 1, 2024 | 87653 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.