Dermott

Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Scurry County. First named in the release with data as of October 1, 2025.

Scurrycounty as printed
138, 345kV
ONCOR, WETTutility
4projects listed

Also printed as: Dermott Switch

A HIFLD substation record has the same name and county: DERMOTT (SCURRY County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Scurry, TX: ERCOT queue, 17 active of 23. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Union - Dermott 138 kV Line Rebuild
Rebuild existing 138 kV Line
ERCOT project 105063 · utility no. R8839 · RPG 26RPG014
ONCOR
Tier 3
Planned
Future tab
138 May 2027 Union to Dermott
Scurry County
Union, Dermott
Ad Hoc TPIT: Rebuild approximately 3.33-mile 345 kV double circuit from WETT's Mhos to Oncor's Dermott Switch station
ERCOT project 110657
WETT
Tier 3
Conceptual
Future tab
345 Feb 2028 Mhos 345 kV to Oncor's Dermott Switch 345 kV station
Scurry County
Mhos, Dermott Switch
Union (fka Sun) - Golden Switch - Dermott 138 kV line Rebuild
Add Permian Basin Reliability Plan Upgrade ID L22C. Upgrade the existing Union (fka Sun) - Golden Switch - Dermott 138-kV line
ERCOT project 99369 · utility no. PB_L22_C
ONCOR
Tier 3
Planned
Future tab
138 Jun 2027 Union to Dermott
Scurry County
Union, Dermott
Union (fka Sun) - Ranger Camp 138 kV Line Rebuild
Add Permian Basin Reliability Plan Upgrade ID L22B. Upgrade the existing Union (fka Sun) - Ranger Camp 138-kV line.
ERCOT project 99520 · utility no. PB_L22_B
ONCOR
Tier 3
Planned
Future tab
138 Jun 2028 Union to Dermott
Scurry County
Union, Dermott

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110657Projected in-service dateOct 2030 → Feb 2028
July 13, 2026110657First listedon the Future tab
June 1, 2026105063First listedon the Future tab
October 1, 202599369First listedon the Future tab
October 1, 202599520First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.