Substation Scout

Deep Creek

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Scurry County. First named in the release with data as of October 1, 2025.

Scurrycounty as printed
138kV
ONCORutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Scurry, TX: ERCOT queue, 17 active of 23. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Union - Deep Creek 138 kV Line Rebuild
Rebuild existing 138 kV line
ERCOT project 105060 · utility no. R8744 · RPG 26RPG014
ONCOR
Tier 3
Planned
Future tab
138 May 2027 Union to Deep Creek
Scurry County
Union, Deep Creek
Deep Creek - Snyder - China Grove 138 kV Line Rebuild
Add Permian Basin Reliability Plan Upgrade ID L22E. Upgrade the existing Deep Creek - China Grove 138-kV line
ERCOT project 99530 · utility no. PB_L22_E
ONCOR
Tier 3
Planned
Future tab
138 Oct 2028 Deep Creek to China Grove
Scurry County
Deep Creek, China Grove

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202699530Projected in-service dateDec 2028 → Oct 2028
June 1, 2026105060First listedon the Future tab
June 1, 202699530Projected in-service dateMay 2028 → Dec 2028
October 1, 202599530First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.