Substation Scout

China Grove

Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Scurry County. First named in the release with data as of June 1, 2016.

Scurrycounty as printed
138kV
ONCORutility
4projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Scurry, TX: ERCOT queue, 17 active of 23. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Snyder - China Grove 69 kV Loop Converstion to 138 kV
Adds part of Permian Basin Reliability Plan Upgrade ID L23. Convert the existing Snyder - Scurry - China Grove and Snyder - Amoco Tap - China Grove 69-kV lines to 138-kV. This phase converts the existing Snyder - Lake Thomas 69 kV Line into 138 kV and reterminates into the new Bluff Creek 138 kV Switch.
ERCOT project 99479A · utility no. PB_L23
ONCOR
Tier 1
Planned
Current-year planned tab
138 Dec 2026 China Grove to Bluff Creek
Scurry County
China Grove, Bluff Creek
Snyder - China Grove 69 kV Loop Converstion to 138 kV
Adds part of Permian Basin Reliability Plan Upgrade ID L23. Convert the existing Snyder - Scurry - China Grove and Snyder - Amoco Tap - China Grove 69-kV lines to 138-kV. This converts the Snyder - Ira - China Grove 69 kV Line into 138 kV and reterminates into the new Bluff Creek 138 kV Switch.
ERCOT project 99479B · utility no. PB_L23
ONCOR
Tier 1
Planned
Future tab
138 Dec 2027 China Grove to Bluff Creek
Scurry County
China Grove, Bluff Creek
Snyder - China Grove 69 kV Loop Converstion to 138 kV
Adds part of Permian Basin Reliability Plan Upgrade ID L23. Convert the existing Snyder - Scurry - China Grove and Snyder - Amoco Tap - China Grove 69-kV lines to 138-kV. This converts the China Grove - Snyder 69 kV Line into 138 kV and reterminates into the new Snyder 138 kV Switch.
ERCOT project 99479C · utility no. PB_L23
ONCOR
Tier 1
Planned
Future tab
138 May 2028 China Grove to Snyder
Scurry County
China Grove, Snyder
Deep Creek - Snyder - China Grove 138 kV Line Rebuild
Add Permian Basin Reliability Plan Upgrade ID L22E. Upgrade the existing Deep Creek - China Grove 138-kV line
ERCOT project 99530 · utility no. PB_L22_E
ONCOR
Tier 3
Planned
Future tab
138 Oct 2028 Deep Creek to China Grove
Scurry County
Deep Creek, China Grove

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202699530Projected in-service dateDec 2028 → Oct 2028
June 1, 202699530Projected in-service dateMay 2028 → Dec 2028
February 1, 202699479AMoved between tabsFuture → Current-year planned
October 1, 202599479AFirst listedon the Future tab
October 1, 202599479BFirst listedon the Future tab
October 1, 202599479CFirst listedon the Future tab
October 1, 202599530First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.