Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Rusk County. First named in the release with data as of June 1, 2025.

Ruskcounty as printed
345kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Rusk, TX: ERCOT queue, 5 active of 6 · SPP queue, 1 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Establish Dorsett 345 kV Switch
ERCOT project 91455 · utility no. R6323
ONCOR
Tier 4
In-Service
Completed tab
345 May 2025
actual 2025-05
Dorsett 345 kV Switch to Dorsett 345 kV Switch
Rusk County
Dorsett 345 kV Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202591455First listedon the Completed tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.