Substation Scout

Saragosa

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Reeves County. First named in the release with data as of October 1, 2018.

Reevescounty as printed
138kV
AEP TNCutility
3projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Install 2nd Bay at Saragosa Substation” — project 72935, as the utility reported it

A HIFLD substation record has the same name and county: SARAGOSA (REEVES County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Reeves, TX: ERCOT queue, 24 active of 27. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Saragosa: Install 2nd Bay
Install 2nd Bay at Saragosa Substation
ERCOT project 72935
AEP TNC
Tier 4
Planned
Completed tab
138 Jan 2026
actual 2025-05
Saragosa
Reeves County
Saragosa
Saragosa: Construct New 138 kV Terminal
Interconnect Cantaloupe Solar to the Saragosa 138 kV station
ERCOT project 86802
AEP TNC
Tier 4
Planned
Future tab
138 Apr 2027 Saragosa
Reeves County
Saragosa
Saragosa: Construct New 138 kV Terminal
Interconnect Bracero Pecan Storage to the Saragosa 138 kV station
ERCOT project 86884
AEP TNC
Tier 4
Planned
Future tab
138 Apr 2028 Saragosa to Bracero Pecan
Reeves County
Saragosa, Bracero Pecan

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202686884Projected in-service dateApr 2027 → Apr 2028
July 13, 202672935Moved between tabsCurrent-year planned → Completed
June 1, 202686884Projected in-service dateApr 2029 → Apr 2027
February 1, 202672935Projected in-service dateJun 2025 → Jan 2026
February 1, 202686884Projected in-service dateFeb 2029 → Apr 2029
October 1, 202572935Projected in-service dateMay 2025 → Jun 2025
October 1, 202586802Projected in-service dateFeb 2029 → Apr 2027
June 1, 202572935Moved between tabsFuture → Current-year planned
June 1, 202586884Projected in-service dateFeb 2027 → Feb 2029
February 1, 202586802Projected in-service dateApr 2027 → Feb 2029
October 1, 202486802First listedon the Future tab
October 1, 202486884First listedon the Future tab
June 1, 202472935Projected in-service dateSep 2024 → May 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first