Saragosa
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Reeves County. First named in the release with data as of October 1, 2018.
Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Install 2nd Bay at Saragosa Substation” — project 72935, as the utility reported it
A HIFLD substation record has the same name and county: SARAGOSA (REEVES County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Reeves, TX: ERCOT queue, 24 active of 27. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Saragosa: Install 2nd Bay Install 2nd Bay at Saragosa Substation ERCOT project 72935 |
AEP TNC Tier 4 |
Planned Completed tab |
138 | Jan 2026 actual 2025-05 |
Saragosa Reeves County |
Saragosa |
| Saragosa: Construct New 138 kV Terminal Interconnect Cantaloupe Solar to the Saragosa 138 kV station ERCOT project 86802 |
AEP TNC Tier 4 |
Planned Future tab |
138 | Apr 2027 | Saragosa Reeves County |
Saragosa |
| Saragosa: Construct New 138 kV Terminal Interconnect Bracero Pecan Storage to the Saragosa 138 kV station ERCOT project 86884 |
AEP TNC Tier 4 |
Planned Future tab |
138 | Apr 2028 | Saragosa to Bracero Pecan Reeves County |
Saragosa, Bracero Pecan |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 86884 | Projected in-service date | Apr 2027 → Apr 2028 |
| July 13, 2026 | 72935 | Moved between tabs | Current-year planned → Completed |
| June 1, 2026 | 86884 | Projected in-service date | Apr 2029 → Apr 2027 |
| February 1, 2026 | 72935 | Projected in-service date | Jun 2025 → Jan 2026 |
| February 1, 2026 | 86884 | Projected in-service date | Feb 2029 → Apr 2029 |
| October 1, 2025 | 72935 | Projected in-service date | May 2025 → Jun 2025 |
| October 1, 2025 | 86802 | Projected in-service date | Feb 2029 → Apr 2027 |
| June 1, 2025 | 72935 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 86884 | Projected in-service date | Feb 2027 → Feb 2029 |
| February 1, 2025 | 86802 | Projected in-service date | Apr 2027 → Feb 2029 |
| October 1, 2024 | 86802 | First listed | on the Future tab |
| October 1, 2024 | 86884 | First listed | on the Future tab |
| June 1, 2024 | 72935 | Projected in-service date | Sep 2024 → May 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.