Substation Scout

Musquiz

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Reeves County. First named in the release with data as of July 13, 2026.

Reevescounty as printed
138kV
AEP TNCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Reeves, TX: ERCOT queue, 24 active of 27. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Musquiz: Install new 138 kV Capacitor Bank
Install new capacitor banks at the Musquiz 138 kV station
ERCOT project 110939
AEP TNC
Tier 4
Conceptual
Future tab
138 Mar 2030 No terminals printed
Reeves County
Musquiz

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110939First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.