Substation Scout

Plowboy

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Nolan County. First named in the release with data as of October 1, 2025.

Nolancounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Nolan, TX: ERCOT queue, 18 active of 18. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Add Permian Basin Reliability Plan Upgrade ID L25D and L25E.
Add Permian Basin Reliability Plan Upgrade ID L25D and L25E. Build Oak Spring - Plowboy 138-kV line. Move the Eskota 138/69-kV transformer 1 to Plowboy.
ERCOT project 99357 · utility no. R8805
ONCOR
Tier 2
Planned
Future tab
138 Sep 2028 Oak Spring to Plowboy
Nolan County
Oak Spring, Plowboy

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202699357Projected in-service dateMay 2028 → Sep 2028
October 1, 202599357First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first