Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Nolan County. First named in the release with data as of February 1, 2015.

Nolancounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Nolan, TX: ERCOT queue, 18 active of 18. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Sweetwater Creek POI - Eskota 69 kV line and convert to 138 kV
Rebuild the Sweetwater Creek POI - Eskota 69 kV line and convert to 138 kV approved as part of the 24RPG040 Oncor Roscoe Area Upgrades Project.
ERCOT project 99359 · utility no. R9000 · RPG 24RPG040
ONCOR
Tier 2
Planned
Future tab
138 Dec 2028 Eskota to Oak Spring
Nolan County
Eskota, Oak Spring

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202599359First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first