Substation Scout

Pinehurst

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Montgomery County. First named in the release with data as of February 1, 2025.

Montgomerycounty as printed
138kV
CNPutility
1projects listed

A HIFLD substation record has the same name and county: PINEHURST (MONTGOMERY County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Montgomery, TX: ERCOT queue, 1 active of 1 · MISO queue, 2 active of 4. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Install new Mill Creek (MLC) distribution substation with (2) 100 MVA transformers.
Convert Pinehurst to unity power factor substation.
ERCOT project 90161C
CNP
Tier 4
Planned
Future tab
138 Dec 2027 Pinehurst
Montgomery County
Pinehurst

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202690161CMoved between tabsCurrent-year planned → Future
October 1, 202690161CProjected in-service dateDec 2026 → Dec 2027
February 1, 202690161CMoved between tabsFuture → Current-year planned
October 1, 202590161CProjected in-service dateAug 2026 → Dec 2026
February 1, 202590161CFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.