Substation Scout

Consavvy

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Midland County. First named in the release with data as of February 1, 2022.

Midlandcounty as printed
138, 345kV
ONCORutility
3projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Midland, TX: ERCOT queue, 7 active of 8 · SPP queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Consavvy – Odessa EHV 345 kV Double Circuit Line Rebuild
Rebuild the existing 345 kV Double-Circuit Line
ERCOT project 81240 · utility no. R3027 · RPG 23RPG029
ONCOR
Tier 1
Planned
Future tab
345 Dec 2029 Consavvy to Odessa EHV
Midland / Ector County
Consavvy, Odessa EHV
Stanton East - Midland Basin - Spraberry 69 kV Line Conversion to 138 kV
Adds part of Permian Basin Reliability Plan Upgrade ID L18. Convert the existing Stanton East - Midland Basin - Spraberry 69-kV line to 138-kV and cut into Consavvy 138 kV Switch to establish the Spraberry - Consavvy 138 kV Line.
ERCOT project 99391A · utility no. PB_L18_A
ONCOR
Tier 3
Planned
Current-year planned tab
138 Dec 2026 Spraberry to Consavvy
Midland County
Spraberry, Consavvy
Stanton East - Midland Basin - Spraberry 69 kV Line Conversion to 138 kV
Add part of Permian Basin Reliability Plan Upgrade ID L18. Convert the existing Stanton East - Midland Basin - Spraberry 69-kV line to 138-kV and cut into Rockhound and Stanton East 138 kV Switches to establish the Consavvy - Rockhound - Stanton East 138 kV Line.
ERCOT project 99391C · utility no. PB_L18_A
ONCOR
Tier 3
Planned
Future tab
138 Dec 2027 Consavvy to Stanton East
Midland County
Consavvy, Stanton East

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202699391AMoved between tabsFuture → Current-year planned
October 1, 202581240Projected in-service dateDec 2028 → Dec 2029
October 1, 202599391AFirst listedon the Future tab
October 1, 202599391CFirst listedon the Future tab
June 1, 202481240First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.