Legend Falls
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Medina County. First named in the release with data as of June 1, 2025.
Described as new. The quoted wording calls this substation new. “New 138kV Legend Falls Substation” — project 84896 title, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Medina, TX: ERCOT queue, 7 active of 8. Same county, not the same substation.
Location
29.4494, -98.8169 · Medina County, TX · view on a map
Read off a planning map. Read off a planning map by matching it to roads and other mapped features. Accurate to about ±100 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: Symbol anchored: the grey rectangle labelled 'Legend Falls Substation' (legend: 'Legend Falls Substation') on CPS Energy / Halff 'Figure 1 Approved Route Map' (7/1/2026, PUC-approved route B2-C2-F2-H2-I2). Read at 200 dpi with a five-point affine fit on OpenStreetMap roads: CR 385 / CR 387 junction (29.44233,-98.81688), CR 385 / CR 381 junction (29.44229,-98.8129), CR 385 west end (29.44227,-98.82618), the CR 381 bend east of the site (29.4465,-98.8103) and the CR 381 bend south of CR 3830 (29.45935,-98.8248); residuals 4-15 m. The rectangle's south-west corner, drawn on CR 381, fits to 29.44912,-98.81813, within ~10 m of the OSM CR 381 centreline. Point is the rectangle's centre (the drawn site is ~240 x 170 m), so +/- ~100 m.
Note: ERCOT's endorsement (23RPG028) had Legend Falls connect to STEC Rio Medina by a ~5.6 mi line; the CCN application says STEC has since added a new San Geronimo substation between them, so the CPS line is ~1.1-2.0 mi to San Geronimo. ERCOT's letter described a 3-terminal ring bus; the application proposes a single bus, single breaker arrangement.
Sources: CPS Energy, Legend Falls 138 kV Substation and Transmission Line Project, Figure 1 Approved Route Map (2026-07-01), p.1 · CPS Energy application to amend its CCN for the Legend Falls 138 kV transmission line project in Medina County (PUCT Docket 59549) (2026-04-06), pp.3-7 · CPS Energy, Legend Falls Substation & Transmission Line Project page (update 07/01/2026: PUC selected Route 17) (2026-07-01) · ERCOT TPIT, projects 84896, 100693, 91708 (release 39, 2026-10-01) · OpenStreetMap: County Roads 381, 385, 387 (Medina County) (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Install a 35.72MVAr Capacitor Bank at Legend Falls Substation ERCOT project 100693 |
CPS/NO Tier 4 |
Planned Future tab |
138 | Jun 2028 | 5259 Medina County |
Legend Falls |
| 23RPG028: STEC Rio Medina Project: New 138kV Legend Falls Substation New 138kV Legend Falls Substation looped into the existing Tally to Texas Research transmission line. This station supports the RPG approved Rio Medina project ERCOT project 84896 · utility no. S-1055 · RPG 23RPG028 |
CPS/NO Tier 2 |
Planned Future tab |
138 | May 2028 | 5259 to 5422, 5430 Medina County |
Legend Falls, This |
| New San Geronimo Substation adds new San Geronimo station on STEC Rio Medina - CPS Legend Falls line ERCOT project 91708 |
STEC Tier 4 |
Planned Future tab |
138 | Jul 2027 | Rio Medina to Legend Falls Medina County |
Rio Medina, Legend Falls |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 84896 | Projected in-service date | Jul 2027 → May 2028 |
| October 1, 2025 | 100693 | First listed | on the Future tab |
| June 1, 2025 | 91708 | First listed | on the Future tab |
| June 1, 2024 | 84896 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.