Fair Oaks Ranch
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Kendall County. First named in the release with data as of June 1, 2021.
No HIFLD substation record has this name in this county (a record of the same name exists in another county).
Generation interconnection requests filed in Kendall, TX: ERCOT queue, 1 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Bergheim - Fair Oaks Transmission Line Upgrade This project will Increase the reliability of transmission facilities on the T238 Bergheim to Fair Oaks 138-kV and T656 Bergheim to Kendall 345-kV 4.1-mile double-circuit transmission line by replacing the aging conductor. ERCOT project 61392 · RPG 22RPG005 |
LCRATSC Tier 4 |
Planned Completed tab |
345 | Mar 2025 actual 2025-03 |
Bergheim to Fair Oaks Ranch/Kendall Comal / Kendall County |
Bergheim, Fair Oaks Ranch, Kendall |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2025 | 61392 | Moved between tabs | Future → Completed |
| February 1, 2025 | 61392 | Projected in-service date | May 2025 → Mar 2025 |
| October 1, 2024 | 61392 | Projected in-service date | Jul 2025 → May 2025 |
| June 1, 2024 | 61392 | Projected in-service date | Nov 2024 → Jul 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.