Substation Scout

Elbow

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Howard County. First named in the release with data as of October 1, 2023.

Howardcounty as printed
138kV
ONCORutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Howard, TX: ERCOT queue, 17 active of 19. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Eiland - Elbow 138 kV Line Rebuild
Add Permian Basin Reliability Plan Upgrade ID L20H. Upgrade the existing Eiland - Elbow 138-kV line
ERCOT project 76669 · utility no. R8665
ONCOR
Tier 3
Planned
Current-year planned tab
138 Dec 2026 Elbow to Eiland
Howard County
Elbow, Eiland
Redberry (fka Elbow) - Prong Moss 138 kV Line Rebuild
Add Permian Basin Reliability Plan Upgrade ID L20C Upgrade the existing Redberry (fka Elbow) - Prong Moss 138-kV line
ERCOT project 98875 · utility no. PB_L20_C
ONCOR
Tier 3
Planned
Future tab
138 May 2027 Elbow to Prong Moss
Howard County
Elbow, Prong Moss

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202676669Moved between tabsFuture → Current-year planned
October 1, 202576669Projected in-service dateMay 2026 → Dec 2026
October 1, 202598875First listedon the Future tab
June 1, 202576669Projected in-service dateDec 2026 → May 2026
June 1, 202476669Projected in-service dateDec 2025 → Dec 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.