Grapeland

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Houston County. First named in the release with data as of October 1, 2025.

Houstoncounty as printed
69kV
ONCORutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Houston, TX: ERCOT queue, 8 active of 8 · MISO queue, 0 active of 2 · SPP queue, 1 active of 2. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade Palestine-Crockett 69 kV Line
Rebuild the Elkhart - Grapeland 69 kV Line
ERCOT project 66202B · utility no. R6182 · RPG 22RPG035
ONCOR
Tier 3
Planned
Current-year planned tab
69 Dec 2026 Elkhart to Grapeland
Anderson / Houston County
Elkhart, Grapeland
Upgrade Palestine-Crockett 69 kV Line
Rebuild the Grapeland - Crockett 69 kV Line
ERCOT project 66202C · utility no. R6182 · RPG 22RPG035
ONCOR
Tier 3
Planned
Future tab
69 Sep 2027 Grapeland to Crockett
Houston County
Grapeland, Crockett

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202666202BProjected in-service dateSep 2026 → Dec 2026
February 1, 202666202BMoved between tabsFuture → Current-year planned
February 1, 202666202BProjected in-service dateDec 2026 → Sep 2026
October 1, 202566202BProjected in-service dateSep 2027 → Dec 2026
October 1, 202566202CFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.