Athens
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Henderson County. First named in the release with data as of February 1, 2015.
Hendersoncounty as printed
69, 138kV
ONCORutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Henderson, TX: ERCOT queue, 7 active of 11. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Tyler to Athens 138 kV line Conversion Establish Foggle Switch, Establish Poynor POI, Echols to Athens 69 kV Line Upgrade ERCOT project 66289B · utility no. R6094 · RPG 22RPG015 |
ONCOR Tier 3 |
In-Service Completed tab |
69 | Dec 2025 actual 2025-12 |
Athens to Echols Henderson County |
Athens, Echols |
| Tyler to Athens 138 kV line Conversion Convert Tyler Switch - Athens 69 kV Line to 138 kV Operation ERCOT project 66289C · utility no. R6094 · RPG 22RPG015 |
ONCOR Tier 3 |
Planned Current-year planned tab |
138 | Sep 2026 | Tyler Switch to Athens Smith / Henderson County |
Tyler Switch, Athens |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| February 1, 2026 | 66289B | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 66289B | Status as reported | Planned → In-Service |
| February 1, 2026 | 66289C | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 66289B | Moved between tabs | Future → Current-year planned |
| October 1, 2024 | 66289B | Projected in-service date | Sep 2026 → Dec 2025 |
| October 1, 2024 | 66289C | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.