Henderson, TX interconnection queue
6 active projects totalling 1,200.7 MW in the ERCOT queue, plus 4 with terminal status (shown greyed).
6active projects
1,200.7active MW
10total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 25INR0095 | Brittlebush BESS | n/r | 597.1 | Battery | Inactive |
| 25INR0094 | Brittlebush Solar | n/r | 594 | Solar | Inactive |
| 28INR0075 | Wild Paw Storage | 345 | 313.2 | Battery | SS Completed, FIS Started, No IA |
| 28INR0029 | Old Fiddler Energy Storage | 138 | 224.6 | Battery | SS Completed, FIS Started, No IA |
| 24INR0355 | Anatole Renewable Energy Storage | 138 | 207.8 | Battery | SS Completed, FIS Completed, IA |
| 23INR0261 | Dodd Solar I | n/r | 201.8 | Solar | Inactive |
| 23INR0464 | Sloan Storage | 138 | 200.9 | Battery | SS Completed, FIS Started, No IA |
| 27INR0014 | Kit Fox Storage | 138 | 153.6 | Battery | SS Completed, FIS Started, No IA |
| 22INR0276 | Trinidad ESS Addition | n/r | 110 | Battery | Inactive |
| 27INR0198 | Musgravite Solar | 138 | 100.6 | Solar | SS Completed, FIS Completed, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.