Henderson County: substations in ERCOT transmission project tracking
8 substation names the workbook places in Henderson County.
| Substation | Projects | Utilities | kV | HIFLD record |
|---|---|---|---|---|
| Athens | 2 | ONCOR | 69, 138 | None |
| Echols | 1 | ONCOR | 69 | None |
| Foggle Switch | 1 | ONCOR | 138 | None |
| Mankin Switch | 2 | ONCOR | 138 | None |
| North Athens Switch (Rayburn) | 1 | ONCOR | 138 | None |
| Seven Points | 2 | ONCOR | 138 | None |
| Tri Corner Switch | 1 | ONCOR | 345 | None |
| Trinidad Switch | 2 | ONCOR | 138, 345 | Name and county agree |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.
Site Scanner