Westchase

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2022.

Harriscounty as printed
138kV
CNPutility
3projects listed

A HIFLD substation record has the same name and county: WESTCHASE (HARRIS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rebuild/reconductor portions of Ckt.05D Missouri City to Westchase as a Hardening Upgrade(26RPG024).
ERCOT project 109761 · RPG 26RPG024
CNP
Tier 3
Planned
Future tab
138 Jun 2028 Westchase to Missouri City
Harris / Fort Bend County
Westchase, Missouri City
Britmoore to Bellaire Ckt.24B Upgrades
Upgrade Ckt.24B Westchase to Hayes to increase thermal limits.
ERCOT project 78485A · RPG 23RPG025
CNP
Tier 3
In-Service
Completed tab
138 May 2025
actual 2025-02
Westchase to Britmoore
Harris County
Westchase, Britmoore
Britmoore to Bellaire Ckt.24B Upgrades
Upgrade Ckt.24B Westchase to Hayes to Britmoore to increase thermal limits. Upgrade Ckt.24 Bellaire equipment and relay limits.
ERCOT project 78485E · RPG 23RPG025
CNP
Tier 3
In-Service
Completed tab
138 May 2025
actual 2025-06
Westchase to Britmoore
Harris County
Westchase, Britmoore

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026109761Projected in-service dateDec 2027 → Jun 2028
July 13, 2026109761Projected in-service dateOct 2027 → Dec 2027
July 13, 2026109761First listedon the Future tab
October 1, 202578485AStatus as reportedPlanned → In-Service
June 1, 202578485AMoved between tabsFuture → Completed
June 1, 202578485EMoved between tabsFuture → Completed
June 1, 202578485EStatus as reportedPlanned → In-Service
February 1, 202578485AProjected in-service dateMay 2026 → May 2025
February 1, 202578485EFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.