Webster

Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2015.

Harriscounty as printed
138kV
CNPutility
5projects listed

A HIFLD substation record has the same name and county: WEBSTER (HARRIS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Webster Distribution Upgrades
Disconnect Webster TR2 from Ckt.92A service and reconnect at other circuit location (see other entry for TR2). Reconnect Webster TR3 as Ckt.92A El Dorado to WEB-TR3 to Kemah.
ERCOT project 100503B
CNP
Tier 4
Planned
Future tab
138 May 2027 Webster to El Dorado /Kemah
Harris County
Webster, El Dorado, Kemah
Webster Distribution Upgrades
Disconnect Webster TR2 from Ckt.92A service and reconnect as Ckt.93A PH Robinson to Webster TR1/TR2 to Webster main bus.
ERCOT project 100503C
CNP
Tier 4
Planned
Future tab
138 May 2027 Webster to PH Robinson /Webster
Harris County
Webster, PH Robinson
Webster Distribution Upgrades
Expand Webster with new TR4 distribution transformer and connect to Ckt.95F Polaris to Webster TR4 to Kemah.
ERCOT project 100503D
CNP
Tier 4
Planned
Future tab
138 May 2027 Webster to Polaris /Kemah
Harris County
Webster, Polaris, Kemah
Upgrade to increase thermal limits as part of FRM upgrades
Upgrade Ckt.06D NASA to Webster to increase thermal limits as part of FRM upgrades
ERCOT project 87479C
CNP
Tier 4
Conceptual
Current-year planned tab
138 Jul 2025 NASA to Webster
Harris County
NASA, Webster
Facility Ratings Methodology (FRM) Upgrades
Upgrade Ckt.06D NASA to Webster to increase thermal limits as part of FRM upgrades
ERCOT project 90232C
CNP
Tier 4
Planned
Current-year planned tab
138 Aug 2026 NASA to Webster
Harris County
NASA, Webster

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202690232CProjected in-service dateJul 2026 → Aug 2026
July 13, 202687479CStatus as reportedPlanned → Conceptual
July 13, 202690232CProjected in-service dateJun 2026 → Jul 2026
July 13, 202690232CProjected in-service dateMar 2026 → Jun 2026
June 1, 202690232CProjected in-service dateJan 2026 → Mar 2026
February 1, 202690232CProjected in-service dateSep 2025 → Jan 2026
October 1, 2025100503BFirst listedon the Future tab
October 1, 2025100503CFirst listedon the Future tab
October 1, 2025100503DFirst listedon the Future tab
October 1, 202590232CProjected in-service dateJul 2025 → Sep 2025
June 1, 202587479CMoved between tabsFuture → Current-year planned
June 1, 202590232CMoved between tabsFuture → Current-year planned
February 1, 202590232CFirst listedon the Future tab
October 1, 202487479CFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.