South Channel
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2017.
A HIFLD substation record has the same name and county: SOUTH CHANNEL (HARRIS County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| TEXPET Customer and Area 138kV Conversions. De-energize 69kV Ckt.16C Deepwater to South Channel. De-energize 69kV Ckt.23A Deepwater to South Channel. De-energize 138/69kV South Channel auto A1 and all remaining South Channel 69kV facilities. Retire all remaining Deepwater 69kV facilities. ERCOT project 109585C |
CNP Tier 4 |
Planned Future tab |
69 | May 2028 | Deepwater to South Channel Harris County |
Deepwater, South Channel |
| MINING 138kV Conversion and BENTON customer substation removal(24RPG033). Rebuild/Repurpose existing 69kV Ckt.16C MINING Switchrack to MINING tap section. Retire MINING Switchrack from Ckt.16C to create new Ckt.16C Deepwater to South Channel. Remove customer-owned BENTON substation from CEHE service. Retire MINING 69kV substation. ERCOT project 67427A · RPG 24RPG033 |
CNP Tier 4 |
Planned Future tab |
69 | Dec 2027 | Deepwater to South Channel Harris County |
Deepwater, South Channel |
| Rebuild and reconductor portions of Ckt.28A to prepare for ETHYL 138kV conversion. Loop into Ckt.96G to create new Ckt.96G PHILIP to ETHYL 138kV to BEARLE. Retire ETHYL 69kV substation and remaining portions of 69kV Ckt.16D and Ckt.28A. Rebuild and reconductor portions of Ckt.28A to prepare for ETHYL 138kV conversion. ERCOT project 75856A |
CNP Tier 4 |
Planned Future tab |
69 | Aug 2027 | ETHYL to South Channel Harris County |
ETHYL, South Channel |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 75856A | Projected in-service date | Mar 2027 → Aug 2027 |
| July 13, 2026 | 109585C | First listed | on the Future tab |
| June 1, 2026 | 67427A | Projected in-service date | May 2027 → Dec 2027 |
| June 1, 2026 | 75856A | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 75856A | Projected in-service date | Dec 2026 → Mar 2027 |
| February 1, 2026 | 75856A | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 75856A | Moved between tabs | Current-year planned → Future |
| October 1, 2025 | 75856A | Projected in-service date | Dec 2025 → Dec 2026 |
| June 1, 2025 | 75856A | Moved between tabs | Future → Current-year planned |
| February 1, 2025 | 67427A | First listed | on the Future tab |
| February 1, 2025 | 75856A | Projected in-service date | May 2025 → Dec 2025 |
| June 1, 2024 | 75856A | Projected in-service date | Apr 2025 → May 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.