Substation Scout

Rhapsody

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2024.

Harriscounty as printed
138kV
CNPutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Bohemian (BOH) 138kV CEHE Substation for Destiny Storage (24INR0397)
Install new CEHE 138kV Bohemian (BOH) substation for generator interconnection to Destiny Storage. Loop Ckt.66K into substation to create new Ckt.66 Crosby to Bohemian to Eastgate.
ERCOT project 78427A
CNP
Tier 4
In-Service
Completed tab
138 May 2026
actual 2026-02
Rhapsody to Crosby/ Eastgate
Harris County
Rhapsody, Crosby, Eastgate
Bohemian (BOH) 138kV CEHE Substation for Destiny Storage (24INR0397)
Install generator lead from Bohemian (BOH) substation to Rhapsody / RHAPSO (RHA) / Destiny Storage
ERCOT project 78427B
CNP
Tier 4
In-Service
Completed tab
138 May 2026
actual 2026-02
Rhapsody to BOHEMI
Harris County
Rhapsody, BOHEMI

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202678427AMoved between tabsCurrent-year planned → Completed
June 1, 202678427AStatus as reportedPlanned → In-Service
June 1, 202678427BMoved between tabsCurrent-year planned → Completed
June 1, 202678427BStatus as reportedPlanned → In-Service
February 1, 202678427AMoved between tabsFuture → Current-year planned
February 1, 202678427BMoved between tabsFuture → Current-year planned
October 1, 202578427AMoved between tabsCurrent-year planned → Future
October 1, 202578427AProjected in-service dateOct 2025 → May 2026
October 1, 202578427BProjected in-service dateJan 2026 → May 2026
June 1, 202578427AMoved between tabsFuture → Current-year planned
June 1, 202578427BProjected in-service dateOct 2025 → Jan 2026
October 1, 202478427AProjected in-service dateSep 2025 → Oct 2025
October 1, 202478427BProjected in-service dateSep 2025 → Oct 2025
June 1, 202478427AProjected in-service dateSep 2024 → Sep 2025
June 1, 202478427BProjected in-service dateSep 2024 → Sep 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first