Plaza

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2022.

Harriscounty as printed
138kV
CNPutility
3projects listed

A HIFLD substation record has the same name and county: PLAZA (HARRIS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
HO Clarke to University 69kV to 138kV Conversion.
Reconductor portions (2.48 miles) of Ckt.06L Knight to Gulfgate as part of Ckt.19A Garden Villas to HO Clarke pre-conversion rebuild.
ERCOT project 109603C · RPG 26RPG011
CNP
Tier 3
Planned
Future tab
138 May 2028 Plaza to Gulfgate
Harris County
Plaza, Gulfgate
Plaza to Grant Ckt.08I Upgrade
Install parallel underground portion of Ckt.08I Plaza to Grant to increase thermal limits.
ERCOT project 70660
CNP
Tier 4
Planned
Current-year planned tab
138 Aug 2026 Plaza to Grant
Harris County
Plaza, Grant
Install Hermann (HER) Distribution Substation
Install Hermann (HER) Distribution Substation. Loop on Ckt.08I to create new Ckt.08 Plaza to Hermann to Grant.
ERCOT project 73332
CNP
Tier 4
Planned
Future tab
138 Oct 2027 Hermann to Plaza/Grant
Harris County
Hermann, Plaza, Grant

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202670660Projected in-service dateJul 2026 → Aug 2026
July 13, 202670660Projected in-service dateJun 2026 → Jul 2026
July 13, 2026109603CFirst listedon the Future tab
July 13, 202670660Projected in-service dateMar 2026 → Jun 2026
February 1, 202670660Moved between tabsFuture → Current-year planned
October 1, 202570660Moved between tabsCompleted → Future
October 1, 202570660Projected in-service dateMar 2025 → Mar 2026
October 1, 202573332Moved between tabsCurrent-year planned → Future
October 1, 202573332Projected in-service dateDec 2025 → Oct 2027
June 1, 202570660Moved between tabsFuture → Completed
June 1, 202573332Moved between tabsFuture → Current-year planned
February 1, 202570660Projected in-service dateFeb 2025 → Mar 2025
October 1, 202470660Moved between tabsCompleted → Future
October 1, 202470660Projected in-service dateMay 2024 → Feb 2025
June 1, 202470660Moved between tabsFuture → Completed

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.